Originally posted by Ben Purnell
View Post
In terms of timing: the factory is on holiday end of next week (22nd) and their are crazy busy in this last week.
So what I agreed is with them (provided we get to 200 wheel orders) is that my down-payment for the low-pressure casting mold and the first samples is on their bank account when they return from holiday (Feb 15th), so they can start right away.
All-in-all a logical ultimate deadline for the down payments is February 7th
In other words - we have another 3 weeks for down payments.
The rest of the timeline is then approximately:
- 6 weeks to make the mold and first samples: end of march
- 1 week my wife to check and improve in china and send samples to Ben, John and myself
- 2 weeks to have Ben, John, myself check the samples and do destructive tests
- 1 week for the chinese to improve on feedback: end of april
- 4 weeks to produce all 200+ wheels: end of may
- 6 weeks to ship to UK and NL: half July
- 2 weeks of customs: end of July
- 2 days shipment within UK/NL: early August